Site Allocations Plan March 2016
List Comments
3 comments.
Respondent | Response Date | Details |
---|---|---|
Environment Agency | 28 Apr 2016 | Site Allocations Plan March 2016 Schedule 1: Proposed large sites for residential development over 10 dwellings (Sites marked with a * are mixed use sites). Weston-super-Mare Total for Weston-super-Mare
Former Weston Library and adjacent BT building - Part tidal Flood Zone 2
|
North Somerset Flood Risk Mana… | 26 Apr 2016 | Site Allocations Plan March 2016 Schedule 1: Proposed large sites for residential development over 10 dwellings (Sites marked with a * are mixed use sites). Weston-super-Mare Total for Weston-super-Mare
Former Weston Library and adjacent BT building - Having looked at the site from an ordinary watercourse, surface water and ground water flooding point of view we have the following comments:
Drainage Category 1 - Easily drained and sustainable drainage could be implemented easily
Reason – 30% reduction in runoff required
|
North Somerset Flood Risk Mana… | 26 Apr 2016 | Site Allocations Plan March 2016 Schedule 1: Proposed large sites for residential development over 10 dwellings (Sites marked with a * are mixed use sites). Weston-super-Mare Total for Weston-super-Mare
Weston Rugby Club - Looking at the site from an ordinary watercourse, surface water and ground water flooding point of view we have the following comments:
Category 2 - Site could be drained by sustainable drainage, however there are constraints and these need to be considered in the design
Reason - areas of 1 in 30 surface water risk - infiltration/soakaway test required and consider whether infiltration can be used as a SuDS technique alongside water storage (in ponds/chambers) and re-use
|