Site Allocations Plan March 2016

List Comments

Search for Comments

Order By
in order

4 comments.

List of comments
RespondentResponse DateDetails
North Somerset Levels IDB 28 Apr 2016

Site Allocations Plan March 2016 Schedule 2: Proposed Employment Sites Service Villages Service Villages: Proposed Employment Allocations

  • Comment ID: 11734177//77
NSLIDB see detail comments
North Somerset Flood Risk Mana… 26 Apr 2016

Site Allocations Plan March 2016 Schedule 2: Proposed Employment Sites Service Villages Service Villages: Proposed Employment Allocations

  • Comment ID: 14550881//90
Park Farm Yatton - Having looked at the site from an ordinary watercourse, surface water and ground water flooding point of view we have the following comments: Category 2 - The site could be drained by sustainable drainage, however there are constraints and these need to be considered in the design Reason – Highly variable permeability. Infiltration/soakaway test required and consider whether infiltration can be used as a SuDS technique alongside water storage (in ponds/chambers) and re-use.
North Somerset Flood Risk Mana… 26 Apr 2016

Site Allocations Plan March 2016 Schedule 2: Proposed Employment Sites Service Villages Service Villages: Proposed Employment Allocations

  • Comment ID: 14550881//93
Estune Business Park (Long Ashton Research Station) - Having looked at the site from an ordinary watercourse, surface water and ground water flooding point of view we have the following comments: Drainage Category 1 - Easily drained and sustainable drainage could be implemented easily Reason - Infiltration/soakaway test required and consider whether infiltration can be used as a SuDS technique alongside water storage (in ponds/chambers) and re-use.
North Somerset Flood Risk Mana… 26 Apr 2016

Site Allocations Plan March 2016 Schedule 2: Proposed Employment Sites Service Villages Service Villages: Proposed Employment Allocations

  • Comment ID: 14550881//94
Havyatt Business Park - Having looked at the site from an ordinary watercourse, surface water and ground water flooding point of view we have the following comments: Drainage Category 2 - The site could be drained by sustainable drainage, however there are constraints and these need to be considered in the design Reason - Opportunities for bespoke infiltration SuDS